Community Notice - Settlement Point Access
Access to portions of the Settlement Point walking track will be disrupted from Monday 14 November while the new steps and boardwalk are constructed.
Please be mindful of contractors working in the area and follow displayed safety signage.
Works will be carried out in accordance with the Cultural Heritage Management Plan which has been approved by the Bunurong Land Council Aboriginal Corporation, and Bass Coast Shire planning permission.
The steps and boardwalk will provide access to the rock platform and direct walkers towards the shoreline, so as to protect the area which is culturally sensitive.
September 2022
|
August 2022
- Community feedback regarding repairs to “The Moorings” section of the Northern Precinct track has been positive.
- Following a site meeting at the Settlement Point dump site (Present: representatives from DELWP, Parks Victoria, contractor, and committee) it was agreed that the contractor prepare a proposal to remove the obvious contaminants from the cliff top and face, and the visible debris from the beach. Minimal excavation is planned.
- Jackets with logo have been ordered for the Weeders Group and others. Tools and gloves are to be purchased.
- Repairs/maintenance will be carried out to sections of Western and Northern Precinct tracks between Albon Street and Settlement Point, Hughes to Cuthbert streets, and at the end of Balcombe Street.
- The “Moorings” section of the Northern Precinct track and the path to the boat ramp in the Jetty Precinct will have planting plans developed and submitted to DELWP for approval.
- Updated quotations for construction of the fishing access at Settlement Pont were agreed. Works in line with the approved CHMP conditions will begin shortly, following cultural heritage induction of contractors by Bunurong Land Council Heritage Advisors.
- DELWP have been notified regarding vegetation destruction that has occurred on the foreshore in several locations.
- Following discussion with a resident, Committee supported facilitation of native grass regeneration adjacent to their house. Volunteers will monitor native grass compared with flatweed growth using the quadrat method.
- A request by the Corinella Boating and Angling Club for a proposed replacement gantry at the boat ramp was agreed to.
- Committee agreed to approach the Corinella Residents and Ratepayers Association to facilitate the proposed fauna survey as a joint initiative.
July 2022
May 2022
|
- Work has commenced on the track opposite The Moorings.
- Speed hump installation on Caravan Park road will occur in June.
- Following a site meeting at the Settlement Point dump site (Present: representatives from DELWP , contractor and committee) it was recommended that a surface scrape of the obvious contaminants on the top and face of the cliff be removed along with any visible debris on the beach.
- Discussion about potentially conducting fauna survey - agreed to wait for the landscape plan to determine.
- Agreed to purchase extra tools and safety vests for the “weeding group” volunteers.
- Ian Morland (DELWP) gave a preliminary rundown on some statistics from the survey in relation to the landscape plan. There were 468 responses and the responses appeared to be relatively evenly spread between those who most valued views and those who valued the native vegetation and wildlife. Ian has since advised a report on the survey will be available on the Engage Victoria website midweek on the week commencing 20th June 2022. The final report should be available by the end of July.
- Boat Ramp Report: A boat has been berthed on the pontoon for approximately a week, restricting availability for other users. Signs prohibiting berthing on the boat ramp jetty have been ordered.
- Maintenance Report: Weed spraying carried out at Jetty Precinct and Northern Precinct. Tables on Jetty Precinct have been removed in anticipation of delivery of changeover tables. Rabbit baiting has been completed with minimal success. Land owners on the Northern Precinct are to be requested to cut grass on a higher setting.
April 2022 |
|
Community Notice - Works Update May/June 2022
- The walking track between Hamilton St and Moorings Place toward Balcombe St will be CLOSED to all pedestrians from the 24th May for several weeks.
- Works to realign and improve the surface of the track will be undertaken over this time.
- We apologise for any inconvenience and we look forward to re-opening this section of the track when the earthworks have been completed.